Program Process
Participation in the Com Standard Offer Program involves five basic phases:
-
Submit an Initial Application (IA) in order for Entergy to screen the project
for measure and Project Sponsor eligibility. If the IA is accepted, Entergy
reserves funds for the Project Sponsor.
-
Prepare and submit a Final Application (FA).
-
Enter into a Standard Offer Program Contract with Entergy.
-
Install the project and submit an Installation Report (IR) to receive an
initial incentive payment (40% Installation Payment).
-
Conduct measurement and verification (M&V) activities and submit a Savings
Report (SR) in order to receive the final energy and demand savings incentive
payment (~60% Performance Payment).
PROGRAM PROCESS DIAGRAM
INITIAL APPLICATION
The first step in the Com SOP process is for the Project Sponsor to submit a
completed Initial Application (IA) for its proposed project. The IA includes
information about the Project Sponsor, information about the nature of the
sites at which the proposed project will be installed, the estimated kW and
kWh impacts, and information regarding the proposed measurement and
verification approach.
Entergy will begin accepting IA's on an announced date and will continue
accepting applications until all funds have been reserved or until the end of
the program year, whichever is earlier.
-
Submittal of Initial Applications will be via a
designated web site.
-
IA's will be considered on a first-come, first-served basis.
-
IA's will be accepted on December 5, 2007 at 10:00 AM CST .
Large Commercial customers may act as their own Project Sponsor. For these
projects, the application process is streamlined, with a number of the
requirements reduced or eliminated.
-
There is no minimum project size; and
-
Qualification thresholds for self-sponsoring customers are reduced in several
areas.
However, the extent to which self-sponsoring customers need to demonstrate
that the proposed measures will actually provide the projected kW and kWh
energy savings remains the same as for projects proposed by Third-Party
Sponsors.
Initial Application Agreement
The IA process requires that the Project Sponsor sign an Initial Application
Agreement. The terms of this agreement are standard for all Project Sponsors
and are not negotiable. Project Sponsors are urged to review the IA Agreement
before submitting a project application.
IA
Agreement
Initial Application Review
Entergy will review each Initial Application (IA) for project sponsor and
measure eligibility. Entergy may request clarification of, or additional
information about, any item submitted as part of the IA.
-
Project Sponsors will have five days to respond to such requests.
-
If the clarification or additional information provided is not sufficiently
responsive, Entergy may, at its sole discretion, request additional
information, or discontinue its evaluation of the submittal.
Any Project Sponsor submitting an unsuccessful Initial Application may reapply
for project funding by submitting another Initial Application. However, the
Project Sponsor will lose its original position in the order of submittal for
reserving funds.
If Entergy approves the Initial Application, the Project Sponsor will be so
notified, in writing.
Non-approval of an Initial Application
Entergy may not approve an Initial Application (IA) if:
-
The IA is incomplete;
-
The IA is received after all funding has been reserved;
-
The Project Sponsor fails to meet program eligibility requirements;
-
The Project Sponsor fails to submit the required supporting documentation;
-
The Project Sponsor is found to have made material misrepresentations in the
IA;
-
The Project Sponsor fails to comply with applicable federal, state and local
laws and regulations; and
-
Changes occur in laws or regulations directly affecting the Com SOP;
FINAL APPLICATION
In the second step in the Com SOP process, Project Sponsors complete a Final
Application (FA). This application describes the proposed measures, project
sites, estimated demand and energy savings, and estimated incentive payments
based on a detailed engineering study and site audit. This application
includes the following information:
-
Detailed information about the host customer site(s);
-
The existing and proposed retrofit equipment inventories, including equipment
counts, equipment efficiencies, and equipment nameplate data;
-
Building occupancy and equipment operating schedules;
-
Engineering calculations estimating energy and demand savings based on the
efficiency of the proposed equipment compared to that of new, minimum-standard
efficiency equipment;
-
A proposed project-specific M&V plan describing how the Project Sponsor will
measure and verify energy and demand savings, the methods for calculating
actual savings, and a schedule for conducting and reporting on M&V activities.
In some cases, pre-installation M&V activities may be required to accurately
estimate savings; and
-
Revised work plan for project design, implementation, operation, and
management, including the anticipated project timeline.
To view the forms that comprise the Final Application, click on
Next Steps.
Project Sponsor - Customer Agreement
The FA includes, as an attachment, a copy of a Project Sponsor-Customer
Agreement. This document must contain language that makes it clear that
Entergy is not a party to the contract to install energy efficiency measures
at the Customer's site. Project Sponsors are urged to review required customer
agreements before submitting a project application.
Customer
Agreement.PDF
Final Application Review
As part of the Final Application review process, Entergy will review the
eligibility of the proposed measures, the accuracy of the savings estimates,
and the comprehensiveness of the M&V plan. The Final Application must be
submitted within 45 days of the date of the IA acceptance for lighting only
projects and within 100 days for all other projects in order to hold reserved
funding. Failure to submit the FA within the day limit may result in loss of
reserved funding.
-
Project Sponsors who do not meet the FA deadline may re-file an Initial
Application for the same project, subject to availability of funds or the
existence of a project waitlist.
-
Entergy may request clarification of, or additional information about, any
item in the application. Project Sponsors will have 10 days to respond to such
requests. If the clarification or additional information is not forthcoming,
Entergy may choose to discontinue its evaluation of the application.
Where FA incentive estimates differ from the incentive funds reserved in the
IA, the FA savings and incentive estimates will take precedence over the IA,
as the FA should include a more detailed and accurate estimate of demand and
energy savings.
-
Where FA estimates are lower than those approved in the IA, the reserved
incentives will be adjusted down accordingly, and excess incentive funds
returned to the remaining program incentive budget.
-
In some cases FA estimates may be higher than approved in the IA. If all
incentive funds have been reserved, and projects are waitlisted, the project
will be limited to the funds reserved in the IA
STANDARD OFFER AGREEMENT
The third step in the Com SOP process is for the Project Sponsor and Entergy
to execute a Standard Offer Agreement outlining the terms and conditions for
the project.
During the course of this Com SOP, Entergy will not entertain proposed
modifications to the Com SOP Agreement. Applicants are urged to review the Com
SOP Agreement prior to submitting a project application. The executed Com SOP
Agreement must be returned to Entergy within 30 days.
2008
Com SOP Agreement
Baseline Inspection
Entergy will conduct a baseline inspection of the project site after the Com
SOP Agreement is executed. The purpose of the inspection is to verify the
baseline conditions documented in the Final Application. The baseline
inspection requires the presence of at least one Project Sponsor
representative who is familiar with the project and the facility so that all
parties can identify any discrepancies simultaneously. The inspection will
verify the following information:
-
All baseline equipment is still in place and operational; and
-
New equipment installation, or old equipment demolition, has not begun.
IMPLEMENTATION PERIOD
The fourth step in the Com SOP process is for the Project Sponsor to install
the energy efficiency measures at the Customer's site. Installation must be
completed by November 15th in the current funding year. That is, projects
receiving incentives from the 2008 Budget must be installed by October 31,
2008.
Installation Report
Project Sponsors must submit an Installation Report (IR) within 30 days of
completing installation. The Installation Report updates any information
proposed in the Final Application that has now been finalized after completion
of the project. The IR typically includes the following information:
The demolished and actual installed retrofit equipment inventories, including
equipment counts, equipment efficiencies, and equipment nameplate data;
-
Updates to building occupancy and equipment operating schedules;
-
Updated engineering calculations estimating energy and demand savings based on
the efficiency of the actual installed equipment compared to that of new,
minimum-standard efficiency equipment; and
-
A final project-specific M&V plan describing how the Project Sponsor will
measure and verify energy and demand savings, the methods for calculating
actual savings, and a schedule for conducting and reporting on M&V activities.
To view the forms that comprise the Installation Report, click on Next Steps.
Post-Installation Inspection
Entergy will contact the Project Sponsor to arrange a post-installation
inspection of the project site after receipt of a complete Installation
Report. The post-installation inspection requires the presence of at least one
Project Sponsor representative who is familiar with the project and the
facility. The inspection shall verify that:
-
The equipment specified in the Installation Report has been installed; and
-
The M&V plan is being followed in accordance with the approved Final
Application.
Installation Payment
Along with the Installation Report, Project Sponsors should submit an invoice
for the first incentive payment - the Installation Payment. This payment is
40% of the incentive estimate approved in the Installation Report.
Entergy's Installation Report review cycle, including a post-installation site
inspection and invoice payment, is 45 days.
PERFORMANCE PERIOD
The fifth and final step in the Com SOP process is called the performance
period. During this time, the actual energy and demand savings that result
from the energy efficiency project are quantified through measurement and
verification (M&V) activities.
Savings Report
The time required to complete M&V activities will range from less than a
month, up to 12 months, depending on the approach chosen. Within 30 days of
the completion of all M&V activities, the Project Sponsor submits a Savings
Report (SR) documenting the project's measured and verified demand and energy
savings. To view the forms that comprise the Savings Report, click on
Next Steps.
Performance Payment
In conjunction with the SR, the Project Sponsor should submit an invoice for
the final incentive payment - the Performance Payment. This payment is based
on the project's verified savings minus the amount paid in the Installation
Payment.
The total incentive payment (installation payment plus performance payment)
cannot exceed the incentive payment listed in the Final Application.
Entergy's Savings Report review cycle, including invoice payment, is 30 days.
OTHER NOTES
If any of the baseline equipment at a project site has been removed prior to
the execution of the Com SOP Agreement, or if any of the proposed
energy-efficient measures have been installed prior to the execution of the
Com SOP Agreement, the project, or the affected portions thereof, will be
disallowed.
Entergy will post updates of available funds on
its web site.
Entergy will not reimburse any Project Sponsor for any costs incurred by
participating in the Com SOP, including costs of preparing the Initial
Application and/or Final Application, reviewing or executing the Com SOP
Agreement, or preparing and submitting Installation or Savings Reports.
|