Project Requirements
PROJECTS MUST BE COMPREHENSIVE
To establish a comprehensive approach to energy efficiency in each individual
household, Project Sponsors are required to evaluate specific measures for
installation, meet minimum criteria, and follow set priorities for financing
of measures through the HTR SOP.
There are three categories of measures - Envelope Energy Waste, Interior
Usage, and HVAC Efficiency. At least one Envelope Energy Waste measure must be
installed in each single-family dwelling unit and multi-family building before
subsequent categories can be considered.
Envelope Energy Waste
-
Single-family insulation measures (all exterior walls, ceiling, or floor with
pier and beam);
-
Multi-family insulation measures (all exterior walls, ceiling, or floors with
pier and beam);
-
Air infiltration control measures (e.g. weatherstripping and caulking); and
-
HVAC duct integrity (repairs, replacements, and sealing with mastic or
aerosol-based duct sealant).
Interior Energy Usage
-
Lighting (compact fluorescent lights with a minimum of 3 hour daily usage);
-
Water heating (shower heads, aerators, pipe insulation, and water heater
jackets); and
-
Refrigerator replacement (energy-efficient refrigerator retrofit).
HVAC Efficiency
-
Room air conditioners (plug-in units allowed);
-
Split systems (complete coil and compressor replacement); and
-
Packaged unit (installed to manufacturer's specifications).
DIAGNOSTIC TESTING REQUIREMENTS
The HTR SOP requires Project Sponsors to perform carbon monoxide and air
infiltration testing to ensure that the health and safety of customers are not
jeopardized by any energy efficiency measure installed as part of this program.
Carbon Monoxide Test
Prior to the installation of any air infiltration control, duct sealing, or
wall insulation measure, carbon monoxide (CO) testing will be conducted for
each residence (single-family and multi-family) with combustion (e.g., natural
gas or propane) equipment or appliances.
Project Sponsors must not install any air infiltration control, duct sealing,
or wall insulation measure that would result in the ambient air CO level
exceeding 9 parts per million at project completion.
Blower Door Test
To evaluate wall insulation, air infiltration control measures, or duct
sealing, the Project Sponsor will conduct pre- and post-installation blower
door tests for each residence (single-family and multi-family). The purpose of
the post-installation test is to verify that the final air exchange rate does
not fall below the minimums set forth in the following table:
Minimum Final Air Exchange Rate*
|
Shielding
|
Single Story
|
Two Story
|
Three or More Stories
|
|
Well Shielded
|
1.18
|
0.95
|
0.83
|
|
Normal
|
0.99
|
0.79
|
0.69
|
|
Exposed
|
0.89
|
0.71
|
0.62
|
* Measured in cubic feet per minute at 50 Pascal per square foot of
conditioned area.
-
Well Shielded is defined as urban areas with high buildings or
sheltered areas, and building surrounded by trees, bermed earth, or higher
terrain.
-
Normal is defined as buildings in a residential neighborhood or
subdivision setting, with yard space between buildings. 80-90% of houses fall
in this category.
-
Exposed is defined as buildings in an open setting with few buildings
or trees around and buildings on top of a hill or ocean front, exposed to
winds.
|
Example The minimum post-installation air exchange rate for an 1800 square
foot, one-story home with normal shielding is 1782 CFM50 (1800 x 0.99). In
order to qualify for the air infiltration control deemed savings, there must
be a minimum 10% reduction between the pre- and post-installation ventilation
rate. Therefore, the pre-installation ventilation rate must be at least 1960
CFM50 (1782 x 110%) in order to be considered for air infiltration control
measures.
|
EFFICIENCY STANDARDS
Entergy has designed the HTR SOP to encourage electric energy efficiency
improvements that go above and beyond the efficiency gains typically achieved
in retrofit or replacement projects. Consequently, energy and demand savings
credit will be based only on reductions that exceed current industry accepted
minimum efficiency standards, where applicable.
|
Example For a Project Sponsor installing a new central air conditioner, the
savings are based on the difference between a high-efficiency unit, e.g., a 13
SEER and a "baseline" unit with a 10 SEER, event though the fifteen-year old
unit being replaced has a SEER of 7.5. In this example, the baseline is the
current federal standard, not the efficiency of the existing unit. The
customer's actual energy savings could be substantially higher.
|
PROJECT REQUIREMENTS
The minimum project size is 10 kW of deemed or measured peak demand savings.
Smaller projects that are similar in nature (type of facility, measures
installed, etc.), but do not meet the minimum size requirements may be
aggregated by the Project Sponsor to meet the minimum project size requirement.
A maximum of 65% of a project's kW and kWh incentive payments may come from
energy-efficient lighting equipment and lighting controls (except day
lighting). Separate projects may also be aggregated to ensure that no more
than 65% of the total project's capacity and energy savings payments are
derived from energy-efficient lighting equipment or lighting controls.
INSTALLATION STANDARDS
No used or reconditioned equipment shall be qualified for incentives. All
equipment shall be new.
Project Sponsor much follow all state and local building codes. Project
sponsor shall be responsible for licenses, building permits and inspections.
Any fees/payments for licenses, building permits, and inspections shall be
paid for by the Project Sponsor.
INELIGIBLE MEASURES
-
Measures that do not raise efficiency above current standards;
-
Measures with an expected life of less than 10 years (except CFL);
-
Cogeneration and self-generation projects;
-
Load shifting/load management measures;
-
Load reductions caused by building vacancies;
-
Measures that rely solely on customer behavior or require no capital
investment;
-
Measures that decrease building plug loads, such as "Green Plugs" or computer
inactivity time-out controls;
-
Measures for which incentives were received under another Entergy program;
-
Repair and maintenance projects;
-
Energy-efficient gas measures when replacing non-electric technologies; and
-
Measures that result in negative environmental or health effects.
OTHER NOTES
As a general rule, measures involving "plug loads" (equipment or appliances
that are plugged into standard electrical outlets) are not permitted. This
restriction may be waived by Entergy if the Project Sponsor provides
reasonable assurance that the energy and/or demand savings associated with
such measures are likely to persist over a 10-year period of time and that
quantifiable energy and/or demand reduction meeting the requirements of the
PUCT's Energy Efficiency Rule can indeed be achieved through the proposed
measure(s).
If the Project Sponsor pursues measures for which deemed savings values have
not been approved by the PUCT, then the Project Sponsor must follow the
International Performance Measurement and Verification Protocol (IPMVP).
Entergy will be the final authority on whether any particular measure is
eligible for incentives.
|